please answer the following question 13

please answer the following question 13

Part 2 Project network/schedule -scheduling and compressing

a schedule

You’ve been asked to manage a project that includes conducting a two-week (10 working days) computer training class. Using the information in Table below, complete the following:

Activity

Immediate Predecessor

Normal Time (days)

Normal Cost

Crashed Time (days)

Crashed Cost

A – Obtain Instructor

None

7

$500

4

$800

B – Locate Room

A

3

$200

2

$350

C – Check Coats

None

6

$500

4

$900

D – Room Open?

C

3

$200

1

$500

E – Schedule Class

B and D

2

$300

1

$350

Schedule Compression:

  1. What is the crash cost per day for each activity?
  2. Which activities should be crashed to meet a project deadline of 10 days with a minimum cost? You may assume that you can partially crash an activity.
  3. What is the new cost after crashing the project?
  4. Fully crash the project to its minimum duration. Prepare a table that shows (for each day the project length is reduced) the project duration, the activities that are crashed, the incremental crash cost, and the total crash cost.
 
Do you need a similar assignment done for you from scratch? We have qualified writers to help you. We assure you an A+ quality paper that is free from plagiarism. Order now for an Amazing Discount!
Use Discount Code "Newclient" for a 15% Discount!

NB: We do not resell papers. Upon ordering, we do an original paper exclusively for you.

Open chat
Need Help?
Need Help? You can contact our live agent via WhatsApp +1(209)962-2652
Feel free to seek clarification on prices, discount, or any other inquiry.