Part 2 Project network/schedule -scheduling and compressing
a schedule
You’ve been asked to manage a project that includes conducting a two-week (10 working days) computer training class. Using the information in Table below, complete the following:
Activity |
Immediate Predecessor |
Normal Time (days) |
Normal Cost |
Crashed Time (days) |
Crashed Cost |
A – Obtain Instructor |
None |
7 |
$500 |
4 |
$800 |
B – Locate Room |
A |
3 |
$200 |
2 |
$350 |
C – Check Coats |
None |
6 |
$500 |
4 |
$900 |
D – Room Open? |
C |
3 |
$200 |
1 |
$500 |
E – Schedule Class |
B and D |
2 |
$300 |
1 |
$350 |
Schedule Compression: